External Tank Assembly Flow
The following is an outline of the construction process for
the Shuttle's huge orange External Tank (ET).

Intertank
- Intertank frame assembly
- Intertank panel installation
- Intertank structural & mechanical installations
- Bldg 420 TPS wedge bonding
- Cell D SLA spray
Oxygen Tank
- LO2 Barrel trim & weld
- Forward OGive trim & weld
- Aft OGive trim & weld
- LO2 tank assembly trim & weld (w/ dome)
- LO2 tank proof test
- Cell E internal clean & iridite ext clean
- Cell B iridite welds SBL & OGive prime
- Cell E aft dome ext clean
- Cell C aft dome prime
- Cell B cure
- Bldg 420 SLA panel bonding & aft dome SOFI
O&I
- VAB aisle stack
- Cell B LO2 Intertank SOFI spray
Dome
- Dome gores trim & weld
- 1:4 dome panel to chord trim & weld
- dome body trim & weld
- dome cap fittings trim & weld
- dome body & cap trim & weld
Hydrogen Tank
- LH2 forward barrel trim & weld
- LH2 aft barrel trim
- Barrel frame installation
- T frame assembly
- LH2 tank assembly trim & weld (w/ dome)
- LH2 tank proof test
- Cell E internal clean & iridite ext clean
- Cell C iridite welds prime & cure
- Bldg 103 SLA panel bonding SOFI fwd dome
- Cell C fwd dome & barrel SOFI spray
- Cell D aft dome SOFI spray
Entire External Tank
- Cell A mate LO2 intertank & LH2
- Final assembly operations
- Test & checkout Building 420
- Load on barge